Chemical and process

Stainless steel mechanical package for new process equipment

PEMEC delivered the mechanical package to pipe up new process equipment at a UK chemical and process site. This was repeat work for an existing client.

ScopeMechanical package
SectorChemical and process
TimelineFebruary to April 2026
ClientRepeat work

Objective

The client had bought new process equipment and needed it piped up, adapting the plant to suit.

Scope

  • Site set-up
  • Stainless steel welding
  • Pipefitting
  • Bolting
  • Hydrotesting

Approach and delivery

The main challenge was a compressed programme. Extra resources were mobilised at the start, so progress stayed ahead of schedule.

Outcome

Delivered on time and within budget, with zero weld repairs required throughout the works.

Results
0weld repairs
On timeand within budget
Repeatclient